MAHARASHTRA KRISHNA VALLEY DEVELOPMENT CORPORATION, PUNE.

Sangli Irrigation Circle, Sangli.

Tembhu Lift Irrigation Project, Tal. Karad, Dist. Satara.

Introduction:

            Tembhu Lift irrigation Scheme has been proposed to irrigate the drought prone area from RL 650 m to 855 m i.e. above the command area of Takari Lift Irrigation Scheme. The project is administratively approved in 1996 for Rs. 1416.59 Crores. The scheme envisages lifting of 22.13 TMC  water from Krishna river to Irrigate 80472 Ha. of lands from, Karad, Kadegaon, Tasgaon, Khanapur, Atpadi, Kavathe Mahankal, Sangola Talukas of Satara, Sangli & Solapur Districts. The water requirement is met with from Koyna, Wang Tarali storage dam and .Krishna river  The revised administrative approved cost is Rs. 2106.09 cores which includes Rs. 1750 crores for work portion. The upto date expenditure on the project is about Rs.1490.17 crores . The second RAA Proposal amounting Rs. 3832.98 crores is sumitted to GOM for Sanction.

 The scheme consists of constructing Barrage across Krishna river at village Tembhu, Tal. Karad, Dist. Satara & Pump House at various stages Rising main, Tunnels & canal, distributory network and the water is lifted in five stages at different location.

Salient Features:

  • Total Command Area                 :           80472 Ha.

  • Discharge                                 :           57.3 Cumecs

  • Total No. of Pumps                   :           111 Nos.

  • Power required                          :           154 MW

  • Total Length of canal                 :           360 Km.

Position of works:

            The Project work were started in 1996. The head work & canal of all five stages were started simultaneously so as to complete the work before May 2000 in order to utilize water as per Krishna Water Dispute Tribunal Award. The present status of the project is given below.

STAGE WISE TECHNICAL DETAILS

Sr. No.

Details

Stage I

Stage II

Stage III

Stage IV

Stage V

Total

1 (A)

1 (B)

3 (A)

3 (B)

1

Storage Details

Through Tembhu Barrage

Through Sump Well

Through Link – I Canal

Through Link – II Canal

Through Link- III Canal

Through feeder Canal

Through Feeder Canal

 

 

 

 

 

 

 

 

2

Pump House

 

 

 

 

 

 

 

 

 

a) No. of pumps (Regular+ Stand by)

b) H.P.

c) Total H.P.

d) Electricity required (MV)

30

+          3

39

+          3

2

+          1

20

+          3

4

+          1

3

+          1

4

+          1

99

+       1

33

39

3

22

5

4

5

100

1950

2200

1400

1940

1990

1075

1235

 

18500

79200

2800

38800

7960

3225

4940

195425

45.82

62.04

2.19

36.62

-

2.53

3.87

153.07

3

Rising Main

 

 

 

 

 

 

 

 

 

Length M.

2050

230

1700

3740

1540

1290

2300

37010

Dia. M

2.5

2.5

1.5

2.5

2.2

1.8

1.8

 

Lines

6

6

1

4

2

1

1

 

4

Designed Static Head

60.83

86.61

57.98

63.67

30.67

37.47

68.33

 

5

Discharge

57.37

57.37

2.88

35.22

14.91

5

4.32

 

6

Length of

--

Link Canal I 15 Km Link cancl II 30 Km

Surli 23 Kamathi 16 Km

Stage 3 A to Ghanad 18 Atpadi Left 15 Ghanad Hivtad 32 Sangola 45 K.Mahan kal 40

Khanapur Tasgaon 106 Km.

Stage 4 to 5 Feeder canal 7 Kachare wadi 35 Km.

Gorewadi 25 Km.

Total 409 Km.

7

Command Area

 

Taluka

 

Karad

-

-

600

-

-

-

-

600

 

Khanapur

-

-

-

-

12975

4000

2000

18375

 

Kadegaon

-

5925

3400

-

-

-

-

9325

 

Tasgaon

-

-

-

-

7700

-

-

7700

 

Atpadi

-

-

-

3652

-

-

-

16000

 

 

-

-

-

12348

-

-

-

-

 

K.Mahankal

-

-

-

7872

-

-

-

7872

 

Sangola

-

-

-

20000

-

-

-

20000

 

Total

-

5925

4000

43872

20675

4000

2000

80472

 

Present Position of Stage I & II of Tembhu Project, Karad

Sr. No.

Name of Work

Present position of work

1

Tembhu Barrage

Work is completed

2

Approch channel 1 (A)

Work is completed

3

Pump House 1 (A)

PH (I) is partially commissioned

4

Control room 1 (A)

Civil work completed 17 panels are installed, Other work in progress.

5

Pressure filter 1 (A)

50% work completed.

6

Anti surge 1 (A)

IRM is tested.

7

Switch yard 1 (A)

Work is completed. C

8

Manifold 1 (A)

Work completed

9

Rising Main 1 (A)

work completed.

10

Railway crossing 1 (A)

work is completed.

11

Pump House Stage 1 (B)

Civil work completed. All pumps are installed. 6 pumps are commissioned.

12

Control room 1 (B)

Civil work is completed & all panels are fixed - 5 panels tested.

13

Switch yard 1 (B)

Work is completed.

14

Pressure filter 1 (B)

Work is completed.

15

Anti surge 1 (B)

Work is completed and IRM is tested.

16

Manifold 1 (B)

Work for 3 line is completed and other is in progress.

17

Rising Main 1 (B)

Work completed.

18

Delevery Chamber 1 (B)

Work completed.

19

Kambale Tunnel

Work completed 100%

20

Link canal-I Km. No. 1 to 15

98% work is completed.

21

Link canal-II Km. 1 to 31

95% work is completed.

22

Pump House Stage – II

Work is completed.

23

Control Room II

Work is completed.

24

Swich Yard – II

Work is completed.

25

Manifold – II

Work completed.

26

Rising Main – II

Work is completed

27

Anti Surge – II

Zero velocity valve is fixed.

28

Delivery Chamber – II

work is completed

29

Surali canal – II K.M. 1 to 23

Work is completed

30

Kamathi canal–II K.M. 1 to 15

Work is completed

31

State Highway Road crossings

Work completed

32

M.D.R./O.D.R. Road crossings

Completed

33

Khanapur – Tasgaon K.M. 1 to 42

K.M. 11 to 20 Earth work completed 21 to 42 and 1 to 10  work are in progress.

34

Khodashi Gated weir

Work is in progress

35

Flood protection wall for Karad Town

Tender process is completed 50%. Work is Completed.

 

Sr. No.

Name of Work

Present position of work

1

Pump House Stage – III

90% work completed.

2

Rising Main Stage – III

Work completed.

3

Devekhindi Tunnel

Excavation completed & lining is in progress.

4

Stage III A to Ghanand Tank 19 K.M. canal

80% work completed.

5

Ghanad-Hivthad canal – 32 K.M.

77% work completed.

6

Kavthe-mahanakal canal 40 K.M.

KM No. 5 to 19 are in progress.

7

Atpadi canal 15 K.M.

KM 3 to 10 are completed.

8

Pump House Stage – IV

55% work completed.

9

Rising Main – V

Work completed.

10

Feder canal stage – IV to V-7 K.M.

68% work completed.

11

Kacharewadi canal – 35 K.M.

---

12

Pump House Stage – V

45% work completed.

13

Rising Main – V

Work completed.

14

Gorewadi canal 25 K.M.

---

15

Sangola Canal KM 50

KM 1 to 25 completed

    16

Visapur Pundi LIS

Tender Process completed

17

KT Weirs – 72 Nos

5 % work completed

 

Sr. No.

Distribution Work

Present position of work

1

Surali Canal

100%

2

Kamathi Canal

1%

3

LK - I

1%

4

LK - II

1%

5

Khanapur Tasgaon Canal

 

 

 

 

 

0%

 

6

Ghanand Hivathad Canal

7

Atpadi Canal

8

Sangola Canal

9

Kavathemahankal Canal

10

Visapur Punandi LIS

11

Kacharewadi Canal

12

Korewadi Canal

 

Year wise Expenditure of the Tembhu Project

Tembhu Lift Irrigation Project
                                                                   Expenditure Statement                                            Rs. in Crore

Year

Year wise Expenditure

Total Expenditure

Work Portion

With ETP

Work Portion

With ETP

1996-97

10.86

13.40

10.89

13.40

1997-98

104.09

128.45

114.95

141.85

1998-99

65.51

80.84

180.46

222.69

1999-00

145.80

179.92

326.26

402.60

2000-01

146.10

180.29

472.36

582.89

2001-02

72.59

89.58

544.95

672.47

2002-03

43.20

53.31

588.15

725.78

2003-04

56.92

70.24

645.07

796.02

2004-05

10.75

13.27

655.82

809.28

2005-06

117.07

144.46

772.89

953.75

2006-07

117.86

140.50

886.75

1094.25

2007-08

21.35

26.35

908.10

1120.60

2008-09

46.80

57.75

954.90

1178.35

2009-10

91.00

112.29

1045.90

1290.64

2010-11

99.41

122.67

1145.31

1413.31

2011-12

62.28

76.85

1207.59

1490.17

 

AIBP -  (Accelerated Irrigation Benefit Program)

             The scheme is partially commissioned and 1020Ha area is irrigated. Now planning commission of Central Govt. is cleared the project for AIBP Assistant of amounting Rs.1972.60Crs. But the project is not  inc;uded in AIBP in the year 2011-12.

Now Finance department of GOI is intimated to process this new project in the year 2012-13. Approval of the Cabinet for continuation of AIBP scheme in the 12 th plan is necessary. Hence the CA under AIBP of amounting Rs.1900.95 crores is submitted to GI. The programme is as below .As per this programme it is planned  to completed the project upto 2017.

Year

Central Govt. Assistant

State Govt. Assistant

Total

Irrigation potential to be created

2012-13

71.19

7.91

79.10

1250

2013-14

398.46

44.27

442.43

7655

2014-15

449.32

49.13

499.25

21000

2015-16

426.46

47.39

473.85

23095

2016-17

365.42

40.60

406.02

26452

Total

1710.85

190.10

19000.95

79452